Number
TR6118
Status Under Construction
Engineer City of Grants Pass
Contractor Timber Mountain Construction
Construction Start
October 2, 2017
Estimated Completion
January 4, 2018
Contract Amount
$185,978.16
Description Installation of approximately 9000 SF of sidewalk and driveway approaches, 6 sidewalk ramps, 500 LF of curb and gutter and associated asphalt paving, storm drain maintenance and driveway restorations.