Savage Street Bridge
Project Details
Number |
TR6165 |
---|---|
Status |
Completed |
Engineer |
ZCS Engineering, Inc. |
Contractor |
Timber Mountain, Inc. |
Construction Start |
May 16, 2016 |
Completion Date |
March 17, 2017 |
Final Contract Amount |
$899,325.90 |
Description |
Removal of a Large Existing Concrete Culvert, Installation of a New 40’ Span Bridge on a Driven Pile Foundation, Installation of Concrete Fish Passage Structure within a Fish Bearing Stream, Replacement of Existing Sanitary Sewer and Water Pipe Section, Installation of (2) Water Quality Storm Drain Catch Basins and Associated Storm Drain Pipe, and Associated Roadway Surface Improvements. Construction will Require Engineered Shoring for Bridge Foundation Installation and the Contractor Must Comply with Project Related Permits (E.G. In-Water Work an a Fish Bearing Stream). |
-
Fish Findings 1
-
Fish Findings 2
-
Fish Findings 3
-
Construction 1
-
Construction 2
-
Construction 3
-
Construction 4
-
Construction 5
-
Construction 6
-
Construction 7
-
Construction 8
-
Construction 9
-
Construction 10
-
Construction 11
-
Construction 12
-
Construction 13
-
Construction 14
-
Construction 15
-
Construction 16
-
Construction 17
-
Construction 18
-
Construction 19
-
Construction 20
-
Construction 21
-
Construction 22
-
Construction 23
-
Construction 24
-
Construction 25
-
Construction 26
-
Construction 27
-
Construction 28
-
Construction 29
-
Construction 30
-
Construction 31
-
Construction 32
-
Construction 33
-
Construction 34
-
Construction 35
-
Construction 36
-
Construction 37
-
Construction 38
-
Construction 39
-
Construction 40