Reinhart Park FY 18 Pedestrian Improvements

Project Details

Project Details, including: project name, number, status, engineer, contractor, start, completion, final amount, and project description
Number
LB6280
Status
Completed
Engineer
City of Grants Pass
Contractor
Copeland Paving, Inc.
Construction Start
August 23, 2017
Final Completion Date
September 25, 2017
Final Contract Amount
$69,394.24
Description
950 LF of Asphalt Path Installed Over Existing Path, 1442 LF of New Asphalt Path on Compacted Base and 2035 SQ. FT. of Concrete Sidewalk.