Number
TR6118
Status
Completed
Engineer
City of Grants Pass
Contractor
Freedom Builders
Construction Start
April 23, 2018
Final Completion Date
June 28 2018
Final Contract Amount
$390,068.10
Description
This Project installed Approximately 17,134 SF of Sidewalk and Driveway Approaches, 27 Sidewalk Ramps, 612 LF of Curb and Gutter and Associated Asphalt Paving, Storm Drain Modifications and Driveway Restorations.