Willow Lane Street Construction 

Project Details

Project Details, including: project name, number, status, engineer, contractor, start, completion, final amount, and project description
Number
TR6325
Status
Completed
Engineer
City of Grants Pass
Contractor
Timber Mountain Construction, Inc.
Construction Start
March 4, 2019
Completion Date
September 5, 2019
Final Contract Amount
$1,383,205.36
Description
The Project Consisted of the Installation of Approximately 3000 LF of Varying Sizes of Storm Drain Pipe and Associated Appurtenances, Approximately 111 LF Of 8” Water Main And 1511 LF of 12” Water Main and Associated Appurtenances, Approximately 101 LF of 60” Irrigation Pipe Crossing, Approximately 1466 Tons of New Asphalt Road Surface, Installation of Approximately 3580 LF of Curb & Gutter, Approximately 21,525 SF of Sidewalk & Driveway Approaches and Associated Sidewalk Ramps, Also Included Striping and Miscellaneous Fencing.

Project Documents