WRP Digester Heat Exchanger Replacement
Project Details
Number |
SE6405 |
---|---|
Status |
Under Construction |
Engineer |
Carollo |
Contractor |
Slayden Constructors, LLC |
Construction Start |
08/01/2022 |
Estimated Completion Date |
07/27/2023 |
Contract Amount |
$2,381,000.00 |
Description | The Work consists of the following distinct projects: Digester Heat Exchanger Installation Project, consisting of: Installation of new drains for pipe trench in the digester control building, construction of a sludge heat exchanger, including CMU block building with membrane roof, associated piping, valves, electrical, controls, and instrumentation modifications and improvements associated with the sludge heat exchanger, demolition of existing structure/piping and appurtenances to accommodate new work, repair and reconstruction of existing improvements affected by the Work, and incidentals for complete and usable facility. Digester Cleaning Project, consisting of: Cleaning of anaerobic digester, handling of associated sludge, replacement of digester gas handling piping and appurtenances, installation of temporary facilities to handle sludge to accommodate digester cleaning, demolition of existing structure/piping and appurtenances to accommodate new work, repair and reconstruction of existing improvements affected by the Work, and incidentals for complete and usable facility. The City may award the projects separately, award both projects to one bidder, award only one of the two projects, or reject all bids upon a finding of the City it is in the public interest to do so. |