Project Details, including: project name, number, status, engineer, contractor, start, completion, final amount, and project description
Number
LB6189
Status
Completed
Engineer
City of Grants Pass
Contractor
CPI Acquisitions
Construction Start
October 12, 2021
Completion Date
October 31, 2021
Final Contract Amount
$82,466.00
Description
The project consisted of the installation of approximately 94 Lineal Feet of Storm Drain Pipe, 262 Lineal Feet of Concrete Curb, 639 SF of Concrete Valley Gutter, and Asphalt Paving.