[ARCHIVED] Steep Slope Hazard Work - Final Time Extension

To Whom It May Concern:


Section 13.104    General Provisions for Construction in the Steep Slope Hazard Area requires that construction work disturbing the soil or affecting the natural drainage and runoff shall be scheduled to terminate not later than October 15th.


Based upon the weather forecast by AccuWeather, a final extension for construction has been provided until November 15, 2018. Section 13.140(3) provides for a maximum thirty (30) day extension.


If you have any questions, please contact Lora Glover, Parks and Community Development Director at (541) 450-6060.